(News Today) - Boeing says the use of "immature" technology caused delays in the delivery of its 787 Dreamliner passenger jet, a project almost three years behind schedule.
"Some of the technology was not as mature as it should have been and we put a global supply chain together without thinking through some of the consequences," Jim Albaugh, president and chief executive of Boeing Commercial Airplanes, said at a forum in the Saudi Arabian capital Riyadh on Sunday.
But he expressed confidence in the aircraft even if production is nearly three years behind schedule.
"It is going to be a magnificent airplane and will be 20 per cent more efficient than the airplanes it is replacing," he said.
Boeing said last week it would delay the delivery of its first 787 unit from February to the third quarter of 2011. The postponement came after a string of technical mishaps and delays slowed the testing program for the jets, heralded as a new generation of highly fuel-efficient, mid-sized aircraft.
An electrical fire during a test flight in November last year forced an emergency landing and ground Dreamliner tests to a halt. But these resumed in December after the company said it had updated the power systems software and conducted rigorous reviews to confirm flight readiness.